The Texas Construction News staff writer
NEW BRAUNFELS – Construction is set to begin Feb. 16 on the Divine Way Rehabilitation Project, a $980,000 initiative aimed at improving streets in the Dove Crossing subdivision.
The project includes a complete mill and overlay of the roadway, replacement of base material with asphalt-stabilized base, and the installation of ADA-compliant ramps. Work will focus on portions of Divine Way, Burleson Drive, and Eagle Pass.
Construction is expected to last approximately four weeks, with completion anticipated in late March 2026.